Drumlins Park, Co. Monaghan

We are constructing a wind farm near Newbliss in County Monaghan. Works commenced in March 2022 and we are now completing the installation of turbines with commercial operation due to start in 2024.

Site details

Drumlins-Park-Site-Stats-Energia-Group-1000-w.jpg

 

The wind farm will consist of 8 wind turbines, generating up to 49MW of renewable energy - enough to meet the annual electricity needs of around 34,000 Irish households.

The development will give rise to a range of benefits, including up to 100 temporary construction jobs. It will also create permanent operation and maintenance roles, as well as ancillary functions.

The development will have a 30-year operational life from the date of commissioning.

Planning permission

Drumlins Park Wind Farm was granted planning permission in July 2020.  To find out more, visit the Monaghan County Council ePlan - Online Planning Details.

Planning permission for the Drumlins Park substation was approved by An Bord Pleanála in November 2021.  Details can be found here: 309119 | An Bord Pleanála (pleanala.ie)

You can view a high resolution version of the site layout map here.

Construction timeline

 

Blade installations underway

All turbine components have now been delivered to site.  Turbines are now being fully assembled - including final tower section, nacelle and blades.

To receive free text construction updates, please email your name, address and mobile number to clo@energia.ie and include DRUMLINS in the subject line. Each text received will allow you to unsubscribe. For details on how we collect, store, secure and process personal data, please read the Energia Group Privacy Statement.

Turbine delivery route 

Turbine components will be transported overnight along the national and regional road network from Waterford Port. Components will travel along the M1 and N2 to Monaghan Town before travelling via the R188, R183 and R189 (via Swans Cross and Newbliss) to the site entrance - arriving before 7am to minimise any disruption for road users. In order to accommodate oversized loads, some permanent and temporary upgrade works have been undertaken at certain points along this route.

Part of the wind farm construction works include permanent upgrades to the L62012 and L62013 local roads.

Community benefit fund

We want local people to see and feel the benefit of renewable energy through our wind farm benefit funds, which support community groups, voluntary organisations and environmental projects situated near our wind farms.

The Drumlins Park community benefit fund will be designed to meet the needs of the local area and will be administered by an independent charitable foundation on behalf of Energia.   It will operate in accordance with Wind Energy Ireland (formerly IWEA) best practice and grants will be made available after one year of wind farm operation.

Working with schools

It’s breath-taking to see a wind turbine up close. The Energia Renewables Operations team are happy to facilitate school visits or classroom talks on wind energy:

  • Discover…how wind turbines generate electricity
  • Learn… about local Energia wind farms
  • Explore... the need for climate action and energy transition

Contact details

If you have any questions about our operational wind farms, development sites, battery storage facilities or renewable energy projects, please contact our Community Liaison Officers by email at clo@energia.ie, or phone +44 (0)78 80432201 or +353 (0)87 9944952.